PROJECT UPDATES

Working Hours: Monday – Friday 7:00 AM – 3:00 PM 

State Road Night Work: Monday – Friday 

Work to remove the old cable on Pearl Ave is set to begin mid-July and is planned to take 6 weeks. Access through Pearl Ave will remain open as police details will be onsite to guide traffic around work zones. Restoration will follow the cable removal; the City of Revere will be setting the curb and our crews will precede with sidewalk restoration. The crews will provide temporary road restoration as the city is set to do final road restoration paving after the project is complete.